Call: (808) 488-9955

CONSTRUCTION ACTIVITIES, PHOTOS AND SCHEDULE

Progress Schedule as of June 28, 2010

Progress Schedule 1 as of May 11, 2010 Progress Schedule 1 as of May 11, 2010 Progress Schedule 1 as of May 11, 2010


Current Construction Activities as of May 28, 2010

  1. BASIC BID WORK ITEMS


    • Jet Grouting

      • Hekaha Street and Kauwa Street
      • Sewerline "A1" (May 28, 2010).
      • Kanuku Street
      • Jet grouting for ground water control, SMH K5 to SMH K6
        (May 3 - 17, 2010).
      • Sewerline "E" (May 3 - 18, 2010).
      • Pit "D1" (May 5 - 17, 2010).
      • Sewerline "D" (May 14 - 17, 2010) .
      • Waterline "C" (May 19 - 20, 2010).
      • Waterline "B" (May 21 - 26, 2010).
      • Lokowai Street
      • Sewerline "C" from SMH C4 to SMH C5 (May 13 - 18, 2010).
      • Lokowai Place
      • Sewerline "C" (May 17 - 18, 2010).
      • Existing 8-inch waterline trench at Sta. 2+43+ and Sta. 5+35+
        (May 27 - 28, 2010).
      • Pahemo Street
      • Pit G2 (May 18 - 21, 2010).
      • Pit G3 (May 14 - 17, 2010).
      • Pit G4 (May 3 - 7, 2010).
      • Pit G5 (May 4 - 7, 2010).
      • Pit G6 (May 5, 2010).
      • Waterline "D", Sta. 0+00+ to Sta. 0+36+, Sta. 0+36+ to Sta. 0+47+, and Sta. 0+47+ to 0+80+ (May 7 - 17, 2010).

    • Shaft/Pit Construction and Backfill

      • Hekaha Street
      • Pit A3.
      • Prepare for pilot tube work (May 10 - 17, 2010).
      • Pour concrete for GBM thrust block (May 12, 2010).
      • Pit A4.
      • Pour concrete for GBM thrust block (May 12, 2010.
      • Pit A8.
      • Excavate and remove concrete from shoring box edges
        (May 13, 2010).
      • Lii Ipo Street
      • Pit J1.
      • Grout floor edges to seal "receiving can" (May 11, 2010).
      • Lokowai Street
      • Pit C1.
      • Grout floor edges to seal "receiving can" (May 10 - 17, 2010).
      • Prepare pit for pilot tube machine (May 14, 2010).
      • Pit C5.
      • Pour concrete for GBM thrust block (May 12, 2010).
      • Pahemo Street
      • Pit K1.
      • Pour concrete for GBM thrust block (May 12, 2010).

    • Sewer Manhole

      • Hekaha Street
      • SMH A1.
      • Remove formwork for top section of lightweight concrete backfill
        (May 4, 2010); pour 4th lift of lightweight concrete backfill
        (May 12, 2010).
      • Place base course and compact (May 12, 2010).
      • Compact base course, and cold patch (May 13, 2010).
      • Weld T-Lock seams (May 14 - 18, 2010).
      • Restore decorative concrete planter box fronting Cutter Ford (May 17, 2010).
      • Holiday Test (May 19, 2010).

    • Potholing/Probing

      • Hekaha Street.
      • Probe for electrical line adjacent to Pit A1 that are to be
        reconstructed to its original location (May 3 - 5).
      • Kanuku Street.
      • Potholed for existing 6-inch sewer lateral and 2-inch gas line at
        Sta. 1+43+ for Sewerline E (May 4, 2010).
      • Existing 8-inch waterline for Waterline "B" (May 6, 2010)
        .
      • Lii Ipo Street.
      • Existing 8-inch waterline for Waterline "B" (May 6, 2010)
      • Lokowai Street.
      • Existing 8-inch waterline for Waterline "C" (May 6, 2010).
      • Existing 6-inch sewer lateral at Sta. 5+96+ for Sewerline "C"
        (May 6 - 7, 2010).
      • Existing 6-inch sewer lateral at Sta. 4+08+ (May 11, 2010)
      • Pahemo Street.
      • Probe for utility crossings (May 5 - 7, 2010).
      • Pothole existing box drain for new Waterline "D" (May 10, 2010).

    • Existing Utility Relocation

      • Hekaha Street.
      • Relocate electrical line to its original location at Pit A1
        (May 5 - 10, 2010).
      • Relocate Oceanic and HTel lines to its original location,
        including reinforced concrete jacket work, backfilling and restoration
        (May 6 - 10, 2010).
      • Lii Ipo Street.
      • Remove section of existing 6-inch VC pipe and concrete cradle;
        raise grade of existing 6-inch sewer lateral at Sta. 3+89+
        (May 4, 2010).
      • Temporarily raise existing 6-inch sewer lateral at Sta. 2+92+
        (May 10, 2010).
      • Temporarily raise existing 6-inch sewer laterals at Sta. 0+99+ and
        Sta. 5+38+ (May 11, 2010).
      • Excavate for new fire hydrant to replace Fire Hydrant No. L-538,
        Sta. 6+29+ to replace Waterline "E" (May 24, 2010).
      • Relocate existing fire hydrant, Sta. 2+17+ (May 21, 2010)).
      • Lokowai Street.
      • Raise grade of existing 6-inch sewer lateral at Sta. 5+96+
        (May 6, 2010).
      • Adjust existing 6-inch sewer lateral at Sta. 3+50+, and Sta. 4+08+
        (May 14, 2010).
      • Adjust existing 6-inch sewer lateral at Sta. 7+09+, and Sta. 7+91+
        for Sewerline "C" (May 18, 2010).
      • Excavate for new fire hydrant lateral at Sta. 2+43+ to replace
        FH No. L-536 (May 24, 2010).
      • Excavate for new fire hydrant laterals at Sta. 5+35+ to replace
        FH No. L-548, and Sta. 7+51+ to replace FH No. L534 (May 25, 2010).
      • Excavate and coordinate for live tap for Waterline "E" connection for
        new fire hydrant lateral at Sta. 7+51+, and Sta. 6+29+,
        Lii Ipo Street, (May 26, 2010).
      • Pahemo Street.
      • Temporarily raise existing 6-inch sewer lateral at Sta. 1+38+ to clear
        new line (May 3 -.
      • Demolish fire hydrant (L-3569), manhole, and installed temporary
        standpipe with valve box frame and cover for relocation of Waterline
        "D" (May 5, 2010).
      • Backfill with SC4, compact base course and cold patch for Waterline
        "F"; pour lightweight concrete from Sta. 0+00+ to Sta. 0+41+
        (May 4 - 7, 2010).

    • Pilot Tube Sewerline Installation

      • Hekaha Street and Lokowai Street.
      • Pit A3 to Pit C1
      • Prepare for pilot tube operations (May 18, 2010).
      • Pilot tube operations (May 19 - 21, 2010).

    • Miscellaneous

      • Demobilize concrete batch plant and silo from Kamehameha Highway
        (May 19, 2010).
      • Remove sewer pedestals and concrete blocks between SMH F3 and SMH
        F4, and remove existing sewer manhole on Olepe Loop
        (May 20 - 21, 2010).
      • Excavate and remove reinforced concrete cradle on Olepe Loop,
        Sta. 1+80+ (May 26, 2010).
      • Excavate and remove abandoned 8-inch sewer line and reinforced
        concrete cradle adjacent to Pit A2 on Hekaha Street
        (May 26 - 27, 2010).


Photos of Recent and Ongoing Construction Activities

May 3 - 10, 2010 - Jet grouting from Pit K5 to Pit K6 on Kanuku Street for ground water control continues.
May 3 - 4, 2010 - Jet grouting of Pit G4 for ground water control in progress.
May 3 - 4, 2010 - Removal of existing 6-inch sewer lateral and reinforced concrete jacket in progress at Lii Ipo Street, Sta. 3+89+.
May 3 - 6, 2010 - Jet grouting for ground water control for Sewerline "E" in progress at Kanuku Street, Sta. 3+32+ to 3+64+.
May 3, 2010 - Recently poured lightweight concrete backfill and placed Omni Balls for Waterline "F", Pahemo Street, Sta. 0+00+ to Sta. 0+41+.
May 4, 2010 - Pothole/probe for existing 6-inch sewer lateral and 2-inch gas line at Kanuku Street, Sta. 1+43+ for Sewerline "E".
May 4, 2010 - FCCC continues to jet grout Pit G5 at Pahemo Street for ground water control.
May 5 - 6, 2010 - Exposing electrical lines to be restored in its original location at Pit A1, Hekaha Street.
May 5, 2010 - Removal of existing fire hydrant valve manhole to facilitate 8-inch water relocation, Waterline "D".
May 6, 2010 - Relocation of electrical lines at Pit A1, Hekaha Street continues.
May 10 - 17, 2010 - Jet grouting for groundwater control for Sewerline "E", Kanuku St., Sta. 0+00+ to 2+22+ in progress.
May 10 - 14, 2010 - Prepare Pit A3 for GBM towards Pit C1.
May 10 - 15, 2010 - Jet grouting for Waterline "D", Pahemo Street, for groundwater control in progress.
May 10, 2010 - Temporarily raise 6-inch lateral to clear GBM at Lii Ipo St., Sta. 2+92+.
May 11 - 13, 2010 - Jet grouting for groundwater control for Pit D1, Kanuku St. begins.
May 11, 2010 - Temporarily raise 6-inch lateral to clear GBM at Lii Ipo St., Sta. 0+99+.
May 11, 2010 - Temporarily raise 6-inch lateral to clear GBM at Lii Ipo St., Sta. 5+38+.
May 12, 2010 - Concrete pour at Pit A4, Hekaha St., for installation of GBM towards Pit F1.
May 12, 2010 - FCCC cleaning Pit A1 in preparation for lightweight concrete pour.
May 12, 2010 - FCCC cleaning Pit A1 in preparation for lightweight concrete pour.
May 13 - 18, 2010 - Jet grouting for ground water control for Sewerline "C" from Pit C4 to Pit C5 at Lokowai St. in progress.
May 13, 2010 - Contractor installing SB frame and cover for SMH A1.
May 13, 2010 - Layout of jet grout columns for Waterline "C", Kanuku St., and Lokowai St.
May 13, 2010 - Layout of jet grout columns for Waterline "C", Kanuku St., and Lokowai St.
May 13, 2010 - Contractor stripping forms for wall brace at Pit A4,Hekaha St.
May 13, 2010 - Contractor removing edges of concrete wall for box shoring.
May 14, 2010 - Contractor fabricating entry seal/ring for Pit A3 for pilot tube lines.
May 14, 2010 - Invert elevation of new 16" line at Pit A3, from Pit A2.
May 14, 2010 - Contractor adjusting 6-inch sewer lateral to clear pilot tubed line below, Sewerline "C", Lokowai St., Sta. 4+08+.
May 14, 2010 - New SMH A1 interior (T-Lock).
May 14, 2010 - New SMH A1 interior (T-Lock).
May 15 - 17, 2010 - Jet grouting of SMH G3 at Pahemo Str. for ground water control in progress.
May 17, 2010 - Sealing of T-Lock sections inside SMH A1, corner of Kamehameha Hway and Hekaha St. continues.
May 17, 2010 - Raising SB frame to road road with brick and mortar; T-lock liner of cone section is below it.
May 17, 2010 - Restoration of decorative concrete wall at corner of Cutter Ford lot.
May 17, 2010 - GBM delivered onsite for initial setup at Pit A3.
May 17, 2010 - Setting up GBM machine in Pit A3 in progress.
May 17, 2010 - Exit ring/seal being installed at Pit C1, Lokowai St.
May 17, 2010 - Haliday teting of Pit A1 T-Lock in progress.
May 18 - 20, 2010 - Jet grouting Waterline "C" for groundwater control continues,Kanuku St. and Lokowai St..
May 18, 2010 - Jet grouting for groundwater control from Pit C4 to Pit E1 at Kanuku Place in progress.
May 18 - 24, 2010 - Jet grouting of Pit G2 at Pahemo St. continues.
May 18, 2010 - Newly restored planter box at Cutter Ford corner.
May 20, 2010 - Augers being pushed through at Pit A3 towards Pit C1.
May 21, 2010 - Removal of abandoned SMH at Olepe Lp., Sta. 1+80+ in progress.
May 21, 2010 - Jet grouting Waterline "B" groundwater control in progress.
May 21, 2010 - Relocating fire hydrant at Lii Ipo St., Sta. 2+17+.
May 21, 2010 - Receiving pilot tube casing at Pit C1.
May 21, 2010 - Auger penetrating exit seal at Pit C1, Lokowai St.
May 21, 2010 - Relocation of fire hydrant at Lii Ipo St., Sta. 6+00+ continues.
May 21, 2010 - Relocation of fire hydrant at Lii Ipo St., Sta. 2+17 continues.
May 24 - 26 , 2010 - Jet grouting Waterline "B" for groundwater control at Kanuku St. and Lokowai St. in progress.
May 24, 2010 - Contractor installed 8x6 tap-in tee with flxmj g.v. for Waterline "E", and pressure testing tee to g.v. at Lii Ipo St.
May 24, 2010 - Installed tap-in tee with flxmh g.v. for fire hydrant lateral at Lii Ipo St., Sta. 6+29+.
May 24, 2010 - Installed new fire hydrant lateral at Lokowai St., Sta. 2+43+.
May 24, 2010 - Prepairing Pit F5 at Lokowai St. to receive pilot tubing from Pit A3.
May 24, 2010 - Installing Romac tapping sleeve and tapping gave valve at Lii Ipo St., Sta. 1+80+ for fire hydrant relocation.
May 24 - 25, 2010 - Pit A8 on Hekaha St. is being prepared for GBM; contractor also laying out vertical and horizontal controls .
TMay 24, 2010 - Pit F5 at Lokowai St. has been retrofitted with existing ring/seal to receive pilot tubing from Pit A3.
May 25, 2010 - Additional jet grouting for SMH J1 to stop water intrusion, Lii Ipo St.
May 25 - 26, 2010 - Relocation of existing fire hydrant at Lokowai St., Sta. 7+55+ in progress.
May 25, 2010 - General maintenance of steel plates at Pit A4, Hekaha St. in progress.
May 25, 2010 - Potholed/probed existing sewer lateral on HekahaSt., Sta. 10+12 .
May 25, 2010 - Contractor Excavatiing for new fire hydrant lateral on Lokowai St., Sta. 5+35+.
May 25 - 26, 2010 - Contractor excavating for new fire hydrant lateral on Lokowai St., Sta. 7+51+.
May 25, 2010 - Temporary modification of sewer lateral at Olepe Lp., Sta. 1+80+ performed to clear Pilot Tubed line beneath.
May 25, 2010 - Precasting of 72-inch floor and riser for SMH in progress at Hawaii Conc. Products.
May 25, 2010 - 72-inch SMH cone section being fabricated at Hawaii Conc. Products.
May 25, 2010 - 72-inch SMH top deck of box section being pre-cast at Hawaii Conc. Products.
May 26, 2010 - Completing jet grouting for ground water control for Waterline "B", Kanuku St. and Lokowai St.
May 26, 2010 - Contractor removing existing 8-inch sewer reinforced concrete cradle.
May 26, 2010 - Jet grouting for ground water control for fire hydrant connection on Lokowai St., Sta. 2+31+.
May 26, 2010 - Hawaii Conc. Products Yard, pouring concrete into mold for cone section of 72-inch SMH.
May 26, 2010 - Hawaii Conc. Products Yard, pouring concrete into inverted mold for floor/riser section of 72-inch SMH.
May 27, 2010 - Pural Water personnel preparing to do 6-inch PVC live tap into 8-inch PVC at Lii Ipo St., Sta. 6+29+.
May 27, 2010 - Pural Water personnel live tapping 8-inch water main for fire hydrant lateral at Lii Ipo St., Sta. 6+29+.
May 27, 2010 - Jet grouting for ground water control for 8-inch water for fire hydrant connection at Lokowai St., Sta. 5+35+.
May 27, 2010 - Contractor continues to remove abandoned 8-inch sewerline with reinforced concrete creadle at Pit A2, Hekaha St..
May 27, 2010 - 16-inch Permalock casing for Pit A3 to Pit C1, Hekaha St., to Lokowai St.
May 27, 2010 - View of full moon from Pit A3 to Pit C1.
May 27, 2010 - Inspecting Permalock casing thickness with a Micrometer.
May 27, 2010 - Excavatio for sewer lateral on Hekaha St., Sta. 9+95 continues.
May 27, 2010 - Newly installed fire hydrant on Lokowai St., Sta. 7+55+.
May 28, 2010 - Probe for existing sewer lateral on Hekaha St., Sta. 10+05+.
May 28, 2010 - By-pass lines being removed from SMH A1 to Pit A2.