CONSTRUCTION ACTIVITIES, PHOTOS AND SCHEDULE

Progress Schedule as of February 10, 2010

Progress Schedule 1 as of February 10, 2010
Progress Schedule 2 as of February 10, 2010


Current Construction Activities

  1. BASIC BID WORK ITEMS



    • Jet Grouting

      • Sewerline "A" alignment pipe support from Pit A3 to Pit A4 (Jan. 4, 2010 - Jan. 16, 2010).
      • Sewerline "A" alignment pipe support from Pit A4 to Pit A8 (Jan. 4 2010 - Jan. 18, 2010).
      • Completed Pit A4 (Dec. 21, 2010 - Jan. 4, 2010).
      • Pit A8 (Jan. 21, 2010 - Jan. 23, 2010).


    • Jet Grout Test Program

      • Second Required Test Program.
      • •Core samplings of jet grout columns at Pit A4 were taken on January 6, 2010.
      • •Excavated and exposed jet grout test columns as required for inspection (Jan. 8, 2010 - Jan. 11, 2010).


    • Jacking/Receiving Shaft A2 (Pit A2)

      • Demolished pipe jack concrete block (Jan. 29, 2010 - Jan. 30, 2010).


    • Receiving Pit Shaft A1 (Pit A1)

      • Exposed existing 42-Inch RCP sewerline and excavate for new Sewer Manhole "A1" (Jan. 11, 2010 - Continuing).


    • Receiving Shaft A3 (Pit A3)

      • Additional jet grouting work was performed to stop water from leaking into the it (Jan. 18, 2010 - Jan. 20, 2010).
      • Installed 8" PVC sight hole at Pit A3 to determine exact location of Tunnel Boring Machine as it enters the pit from Pit A4 (Jan. 26, 2010 - Jan. 27, 2010).
      • Constructed exit beam and seal for Tunnel Boring Machine from Pit A4 (Jan. 27, 2010 - Jan. 29, 2010).


    • Jacking/Receiving Shaft A4 (Pit 4)

      • Installed I-Beam whalers to reinforce sheet piles (Jan. 11, 2010 - Jan. 12, 2010).
      • Pit excavation completed (Jan. 13, 2010 - Jan. 15, 2010).
      • Completed construction of concrete slab for microtunneling rig (Jan. 14, 2010 - Jan. 16, 2010).
      • Installed entry seal ring and assembled microtunneling equipment (Jan. 18, 2010 - Jan. 21, 2010).


    • Receiving Shaft A8 (Pit A8)

      • Jet grouting (Jan. 21, 2010 - Ongoing).


    • Microtunneling & Steel Casing

      • Microtunneling and jacking steel casing from Pit A4 to Pit A3, (Jan. 22, 2010 - Jan. 28, 2010).
      • Installed 8" PVC sight hole at Pit A3 to determine exact location of Tunnel Boring Machine as it enters the pit (Jan. 26, 2010 - Jan. 27, 2010).


    • PVC Pipe

      • Installed new 16-Inch PVC sewerline from Pit A2 to Pit A1, corner of Waimalu Shopping Center on Hekaha Street, to corner of Kamehameha Highway and Hekaha Street (adjacent to Cutter Ford), Sewerline "A" Sta. 3+62.26 to Sta. 0+00 (Jan. 4, 2010 - Jan. 5, 2010). Total pipe installed between Pit A2 and A1 is 344 feet, 5 inches.
      • Pumped 105 C.Y. of lightweight concrete into annulus space between sewerline and steel casing from Pit A1 to Pit A2 on January 9, 2010.
      • Pressure hydro-tested 16-inch PVC sewerline on January 11, 2010.


    • Existing Utility Relocation

      • Installed new 16-Inch PVC sewerline from Pit A2 to Pit A1, corner of Waimalu Shopping Center on Hekaha Street, to corner of Kamehameha Highway and Hekaha Street (adjacent to Cutter Ford), Sewerline "A" Sta. 3+62.26 to Sta. 0+00 (Jan. 4, 2010 - Jan. 5, 2010). Total pipe installed between Pit A2 and A1 is 344 feet, 5 inches.
      • Completed relocation of 24-Inch Drainline in conflict with Pit A8, Hekaha Street, Sta. 11+31+ (Jan. 4, 2010 - Jan. 5, 2010).
      • Completed relocation of 8-Inch Drainline in confliect with Pit A8, Hekaha Street, Sta. 11+25+ (Jan. 4, 2010 - Jan. 5, 2010).


    • Inclinometer

      • Installed inclinometer casing adjacent to Pit A4 (Jan. 5, 2010).


  2. ADDITIVE ALTERNATES - SEWERLINES A1, C, D, E, J AND K WORK ITEMS



    • Pothole Existing Utilities

      • "Potholed" for existing 6-inch sewerline for Sewerline "K" on Pahemo Street, Sta. 2+14+(Jan. 20, 2010).
      • "Pothole" for existing 24-inch drainline for Sewerline "K" on Pahemo Street, Sta. 2+14+ (Jan. 20, 2010).


      • Existing Utilities Relocation

        • None.


      • Jet Grouting

        • None.


Photos of Recent and Ongoing Construction Activities

Tuesday, December 1, 2009 - Contractor begins with the excavation of Pit A1.
Tuesday, December 1, 2009 - Crew removing section concrete thrust block in Pit A2 that was used for pipe jacking operation from Pit A2 to Pit A3.
Tuesday, December 1, 2009 - Jet grouting operation for Sewerline "A" pipe alignment in progress near the Waimalu Shopping Center driveway at Hekaha Street.
Wednesday, December 2, 2009 - Jet grouting for Sewerline "A" pipe alignment from Pit A2 to Pit A1 on Kamehameha Highway being done at night.
Thursday, December 3, 2009 - Re-assembling microtunneling equipment in Pit A2 for drilling and pipe jacking from Pit A2 to Pit A1.
Thursday, December 3, 2009 - Crew placing "trailing can" behind the "steering can".
Friday, December 4, 2009 - Contractor continues Pit A1 excavation.
Friday, December 4, 2009 - Unloading of 38" Permalok steel casing pipe in place for pipe jacking operation at Pit A2.
Monday, December 7, 2009 - Steel plate in place to protect existing 42" sewerline while crew uses mini-excavator to excavate Pit A1.
Monday, December 7, 2009 - Microtunneling and pipe jacking from Pit A2 to Pit A1 continues.
Monday, December 7, 2009 - Power brooming dirt and debris off roadway at Hekaha Street and Kamehameha intersection.
Tuesday, December 8, 2009 - Coring of jet grout column along Sewerline "A" pipe alignment at Sta. 0+75+ for test sampling.
Tuesday, December 8, 2009 - Derrick Corp. soil separator at work maintaining flow of water through microtunneling machine while extracting soil and debris.
Wednesday, December 9, 2009 - Locating abandoned 8" sewerline prior to Pit A4 (as shown on VE drawings) sheetpiling work.
Wednesday, December 9, 2009 - Layout to temporarily relocate an 18" drainline around Pit A4 sheetpile wall.
Thursday, December 10, 2009 - Trench excavation to temporarily relocate existing 18" drainline around Pit A4 sheetpile wall.
Thursday, December 10, 2009 - Contractor mobilized another jet grout plant at the northwest corner of Kanuku Street and Lii Ipo Street.
Thursday, December 10, 2009 - Temporary 18" drainline installation around Pit A4 sheetpile wall in progress.
Friday, December 11, 2009 - Decomposed wood is encountered, starting at Sta 0+50+.
Friday, December 11, 2009 - Pit A8 as shown on VE is laid out along with location of existing 6" sewerline and 24" drainline that will be temporarily relocated outside pit area.
Friday, December 11, 2009 - Relocating existing 6" sewerline away from Pit A8 in progress.
Monday, December 14, 2009 - Jet grouting for Sewerline "E" pipe alignment at Kanuku Street, from Sta 1+00 to 1+50+.
Monday, December 14, 2009 - Jet groutiing (second crew) for Sewerline "J" pipe alignment at Lii Ipo Street, from Sta 7+78 to 8+68+.
Monday, December 14, 2009 - Crew places shoring blocks in preparation for relocation of existing 6" waterline at Pit A4.
Tuesday, December 15, 2009 - Giken Silent Piler is mobilized in place at Pit A4.
Wednesday, December 16, 2009 - Drving sheetpiles for Pit A4 with Giken Silent Piler.
Wednesday, December 16, 2009 - Traffic is rerouted at Hekaha Street while crew drives sheetpiles for Pit A4.
Wednesday, December 16, 2009 - Crew begins installing exit seal at Pit A1.
Thursday, December 17, 2009 - Crew uses smaller jet grout equipment (Soil-Mec 103) due to overhead wires to jet grout Sewerline "E" pipe alignment.
Thursday, December 17, 2009 - Jet grouting for Sewerline "J" pipe alignment continues.
Thursday, December 17, 2009 - HECO blanketed overhead high voltage lines that are in close proximity to work area prior to the pile driving operation.
Friday, December 18, 2009 - Jet grout column layout for Sewerline "K" pipe alignment.
Friday, December 18, 2009 - With the sheetpiles in place, contractor levels the area with basecourse material.
Friday, December 18, 2009 - With the microtunneling from Pit A2 to A3, and A2 to A1 complete, the crew dismantles Derrick Soil Separator.
Friday, December 18, 2009 - Crew lays out grid for jet grout colums for Pit A4.
Monday, December 21, 2009 - Contractor removes soil separator bin from the Derrick Soil Separator.
Tuesday, December 22, 2009 - Contractor begins to store 16" PVC at baseyard, covering it for UV protection.
Wednesday, December 23 2009 - Contractor continues to jet grout for Pit A4.
Monday, December 28, 2009 - Jet grouting of Pit A4 continues.
Monday, December 28, 2009 - Jet grout column layout for Sewerline "A" pipe alignment from Pit A4 to Pit A8.
Tuesday, December 29, 2009 - Jet grouting for Sewerline "A" pipe alignment from Pit A3 to Pit A4.
Tuesday, December 29, 2009 - Contractor locating existing gasline at Hekaha Street, Sta. 6+60+.
Wednesday, December 30, 2009 - Contractor continues to jet grout Pit A4 and Sewerline "A" pipe alignment from Pit A3 to Pit A4.
Wednesday, December 30, 2009 - Crew continues to jet grout Pit A4.