Community Planning & Engineering
Call: (808) 488-9955
|
|
| Tuesday, December 1, 2009 - Contractor begins with the excavation of Pit A1. |
|
| Tuesday, December 1, 2009 - Crew removing section concrete thrust block in Pit A2 that was used for pipe jacking operation from Pit A2 to Pit A3. |
|
| Tuesday, December 1, 2009 - Jet grouting operation for Sewerline "A" pipe alignment in progress near the Waimalu Shopping Center driveway at Hekaha Street. |
|
| Wednesday, December 2, 2009 - Jet grouting for Sewerline "A" pipe alignment from Pit A2 to Pit A1 on Kamehameha Highway being done at night. |
|
| Thursday, December 3, 2009 - Re-assembling microtunneling equipment in Pit A2 for drilling and pipe jacking from Pit A2 to Pit A1. |
|
| Thursday, December 3, 2009 - Crew placing "trailing can" behind the "steering can". |
|
| Friday, December 4, 2009 - Contractor continues Pit A1 excavation. |
|
| Friday, December 4, 2009 - Unloading of 38" Permalok steel casing pipe in place for pipe jacking operation at Pit A2. |
|
| Monday, December 7, 2009 - Steel plate in place to protect existing 42" sewerline while crew uses mini-excavator to excavate Pit A1. |
|
| Monday, December 7, 2009 - Microtunneling and pipe jacking from Pit A2 to Pit A1 continues. |
|
| Monday, December 7, 2009 - Power brooming dirt and debris off roadway at Hekaha Street and Kamehameha intersection. |
|
| Tuesday, December 8, 2009 - Coring of jet grout column along Sewerline "A" pipe alignment at Sta. 0+75+ for test sampling. |
|
| Tuesday, December 8, 2009 - Derrick Corp. soil separator at work maintaining flow of water through microtunneling machine while extracting soil and debris. |
|
| Wednesday, December 9, 2009 - Locating abandoned 8" sewerline prior to Pit A4 (as shown on VE drawings) sheetpiling work. |
|
| Wednesday, December 9, 2009 - Layout to temporarily relocate an 18" drainline around Pit A4 sheetpile wall. |
|
| Thursday, December 10, 2009 - Trench excavation to temporarily relocate existing 18" drainline around Pit A4 sheetpile wall. |
|
| Thursday, December 10, 2009 - Contractor mobilized another jet grout plant at the northwest corner of Kanuku Street and Lii Ipo Street. |
|
| Thursday, December 10, 2009 - Temporary 18" drainline installation around Pit A4 sheetpile wall in progress. |
|
| Friday, December 11, 2009 - Decomposed wood is encountered, starting at Sta 0+50+. |
|
| Friday, December 11, 2009 - Pit A8 as shown on VE is laid out along with location of existing 6" sewerline and 24" drainline that will be temporarily relocated outside pit area. |
|
| Friday, December 11, 2009 - Relocating existing 6" sewerline away from Pit A8 in progress. |
|
| Monday, December 14, 2009 - Jet grouting for Sewerline "E" pipe alignment at Kanuku Street, from Sta 1+00 to 1+50+. |
|
| Monday, December 14, 2009 - Jet groutiing (second crew) for Sewerline "J" pipe alignment at Lii Ipo Street, from Sta 7+78 to 8+68+. |
|
| Monday, December 14, 2009 - Crew places shoring blocks in preparation for relocation of existing 6" waterline at Pit A4. |
|
| Tuesday, December 15, 2009 - Giken Silent Piler is mobilized in place at Pit A4. |
|
| Wednesday, December 16, 2009 - Drving sheetpiles for Pit A4 with Giken Silent Piler. |
|
| Wednesday, December 16, 2009 - Traffic is rerouted at Hekaha Street while crew drives sheetpiles for Pit A4. |
|
| Wednesday, December 16, 2009 - Crew begins installing exit seal at Pit A1. |
|
| Thursday, December 17, 2009 - Crew uses smaller jet grout equipment (Soil-Mec 103) due to overhead wires to jet grout Sewerline "E" pipe alignment. |
|
| Thursday, December 17, 2009 - Jet grouting for Sewerline "J" pipe alignment continues. |
|
| Thursday, December 17, 2009 - HECO blanketed overhead high voltage lines that are in close proximity to work area prior to the pile driving operation. |
|
| Friday, December 18, 2009 - Jet grout column layout for Sewerline "K" pipe alignment. |
|
| Friday, December 18, 2009 - With the sheetpiles in place, contractor levels the area with basecourse material. |
|
| Friday, December 18, 2009 - With the microtunneling from Pit A2 to A3, and A2 to A1 complete, the crew dismantles Derrick Soil Separator. |
|
| Friday, December 18, 2009 - Crew lays out grid for jet grout colums for Pit A4. |
|
| Monday, December 21, 2009 - Contractor removes soil separator bin from the Derrick Soil Separator. |
|
| Tuesday, December 22, 2009 - Contractor begins to store 16" PVC at baseyard, covering it for UV protection. |
|
| Wednesday, December 23 2009 - Contractor continues to jet grout for Pit A4. |
|
| Monday, December 28, 2009 - Jet grouting of Pit A4 continues. |
|
| Monday, December 28, 2009 - Jet grout column layout for Sewerline "A" pipe alignment from Pit A4 to Pit A8. |
|
| Tuesday, December 29, 2009 - Jet grouting for Sewerline "A" pipe alignment from Pit A3 to Pit A4. |
|
| Tuesday, December 29, 2009 - Contractor locating existing gasline at Hekaha Street, Sta. 6+60+. |
|
| Wednesday, December 30, 2009 - Contractor continues to jet grout Pit A4 and Sewerline "A" pipe alignment from Pit A3 to Pit A4. |
|
| Wednesday, December 30, 2009 - Crew continues to jet grout Pit A4. |
|