Call: (808) 488-9955

CONSTRUCTION ACTIVITIES, PHOTOS AND SCHEDULE

January 2010

Progress Schedule as of January 7, 2010

Progress Schedule 1 as of January 7, 2010
Progress Schedule 2 as of January 7, 2010


January Construction Activities

  1. BASIC BID WORK ITEMS



    • Jet Grouting

      • Completed jet grouting for Sewerline "A" pipe alignment from Pit A2 to Pit A1.
      • Sewerline pipe alignment from Pit A3 to Pit A4 in progress.
      • Pit A4 in progress.
      • Lay out and mark Pit A4 to Pit A8 jet grout columns for Sewerline "A" pipe alignment recently completed.
      • Additional jet grout crew mobilized to assist with jet grouting operations.


    • Jacking/Receiving Shaft for Microtunneling Work at SMH A2 (Pit A2)

      • Contractor re-aligned tunnel machine to microtunnel from Pit A2 to Pit A1.


    • Receiving Pit at SMH A1 (Pit A1)

      • Excavation work completed.
      • Exit ring installed.


    • Through Pit A3 (SMH A3)

      • Pipe jacking from Pit A2 to Pit A3 completed.
      • Exit ring sealed until SMH 3 is constructed.


    • Jacking/Receiving Pit A4 (SMH 4)

      • Sheetpiling recently completed.
      • Inclinometer casing recently installed.
      • Jet grouting in progress.


    • Microtunneling

      • Microtunneling from Pit A2 to Pit A1 completed.


    • PVC Pipe Installation

      • Scheduled to begin on the first week of January, 2010.


    • Existing Utility Relocation

      • Temporary relocation of 18-inch drainline outside of Pit A4 area completed.
      • Temporary relocation of 6-inch waterline outside of Pit A4 completed.
      • Temporary relocation of 6-inch sewerline completed.


  2. ADDITIVE ALTERNATES - SEWERLINES A1, C, D, E, J AND K WORK ITEMS



    • Pothole Utilities

      • No potholing work done in December, 2009.


      • Existing Utilities Relocation

        • None.


      • Jet Grouting

        • Sewerline "E" pipe alignment at Kanuku Street, from Sta. 1+00 to 1+50+ in progress.
        • Sewerline "J" pipe alignment at Lii Ipo Street, from Sta. 7+78 to 8+68+ in progress.
        • Sewerline "K" pipe alignment in progress.