| Monday, February 1, 2010 - Jet grouting for inclinometer piping/shaft at Pit A8 in progress. |
|
| Monday, February 1, 2010 - Newly constructed concrete for inclinometer casing at Pit A8. |
|
| Monday, February 1, 2010 - Temporary sewer by-pass line being installed at Pahemo Street. |
|
| Tuesday, February 2, 2010 - Crew preparing to install 16” PVC Hobas pipe form Pit A4 to Pit A3. |
|
| Tuesday, February 2, 2010 - Temporary sewer by-pass system connecting existing 8" sewerline being installed at Pahemo Street. |
|
| Tuesday, February 2, 2010 - Contractor backfilling 6" sewerline lateral on Pahemo Street. |
|
| Wednesday, February 3, 2010 - Jet grouting on Pahemo Street for water control continues, Sta. 6+75+ to Sta. 7+00+. |
|
| Wednesday, February 3, 2010 - Brace for I-Beam support at Pit A8 to support steel plates is being welded onto shoring box. |
|
| Thursday, February 4, 2010 - New layout for tunnel boring machine equipment track at Pit A4 towards Pit A8. |
|
| Thursday, February 4, 2010 - Contractor is placing and compacting 3B base course at Pit A8. |
|
| Friday, February 5, 2010 - Repositioning microtunneling equipment/system at Pit A4 towards Pit A8; concrete block for jacking plate is being formed. |
|
| Friday, February 5, 2010 - Temporary by-pass sewer line is being installed at Pahemo Street. |
|
| Friday, February 5, 2010 - Jet grouting for water control on Pahemo Street continues. |
|
| Saturday, February 6, 2010 - "Full Moon" view of 16" PVC from Pit A3 to Pit A4. |
|
| Saturday, February 6, 2010 - View of annuls space between steel casing and 16" PVC pipe. |
|
| Saturday, February 6, 2010 - View of end section of steel casing; annulus space sealed with brick and mortar, and vent pipes installed for grouting of annlus space with lightweight concrete. |
|
| Saturday, February 6, 2010 - "Full Moon" view of 16" PVC pipe from Pit A4 towards Pit A3. |
|
| Saturday, February 6, 2010 - Contractor installing entry seal onto sheet pile wall at Pit A4 towards Pit A8. |
|
| Monday, February 8, 2010 - Microtunneling crew cutting sheet pile wall inside entry ring seal with oxygen lancer. |
|
| Monday, February 8, 2010 - Laser guidance system is being calibrated in Pit A4 prior to microtunneling to Pit A8. |
|
| Monday, February 8, 2010 - Crew inserting tunnel boring machine and steering can into entry seal towards Pit A8. |
|
| Monday, February 8, 2010 - Jet grouting for water control at Pahemo Street continues (Hole Nos. 92 – 94, 33, 38, 40 and 98). |
|
| Tuesday, February 9, 2010 - Preparing existing sewer manhole for removal, and locating existing sewerlines at Pahemo Street, Sta. 2+15+. |
|
| Tuesday, February 9, 2010 - Preparing existing sewer manhole for removal, and locating existing sewerlines at Pahemo Street, Sta. 2+15+. |
|
| Tuesday, February 9, 2010 - Jet grouting for ground water control continues (#95, 97, 46, 99, 48, 101, 103, 105). |
|
| Tuesday, February 9, 2010 - Removal of existing SMH at Pahemo Street, Sta. 2+15+ in progress. |
|
| Wednesday, February 10, 2010 - Jet grouting for water control continues at Pahemo Street (#57, 55, 112, 110, 108, 52, 50, 106, 104, 102, 100, 111). |
|
| Thursday, February 11, 2010 - Microtunneling operation from Pit A4 to Pit A8 continues. |
|
| Thursday, February 11, 2010 - Microtunneling operation from Pit A4 to Pit A8 continues. |
|
| Friday, February 12, 2010 - View of microtunneled material from Derrick Soil Separator during microtunneling operation from Pit A4 to Pit A8. |
|
| Friday, February 12, 2010 - Steel casing #25, and #26 are being jacked towards Pit A8 from Pit A4. |
|
| Saturday, February 13, 2010 - Steel casing #31 is being jacked towards Pit A8 from Pit A4. |
|
| Saturday, February 13, 2010 - Microtunneling crew checking site pipe. |
|
| Saturday, February 13, 2010 - Steel casing #35 is being jacked towards Pit A8 from Pit A4. |
|
| Tuesday, February 16, 2010 - Excavation around bell end of existing 42” RCP at Pit A1 in progress. |
|
| Tuesday, February 16, 2010 - Contractor setting receiving collar onto face of exit wall form for Pit A8. |
|
| Tuesday, February 16, 2010 - Forming exit wall at Pit A8 in progress. |
|
| Tuesday, February 16, 2010 - Jet grouting for ground water control continues at Pahemo Street (#59, 61, 63, 7, 65 – Sta. 6+03+ to 6+30+). |
|
| Wednesday, February 17, 2010 - Pouring of 4000 psi concrete for exit wall and receiving collar in progress at Pit A8. |
|
| Wednesday, February 17, 2010 - Unloading new 16" PVC pipes for Sewerline "A", Pit A4 to Pit A8. |
|
| Wednesday, February 17, 2010 - Jet grouting for ground water control continues at Pahemo Street (#58, 60, and 9; Sta. 6+03+ to 6+30+). |
|
| Wednesday, February 17, 2010 - Excavation under bell ends of existing 42" RCP continues at Pit A1. |
|
| Wednesday, February 17, 2010 - Jet grouting for ground water control continues at Pahemo Street, and O A Street (#1, 3 and 5). |
|
| Thursday, February 18, 2010 - Last steel casing towards Pit A8 from Pit A4 is being installed. |
|
| Thursday, February 18, 2010 - End seal collar locks are being installed. |
|
| Thursday, February 18, 2010 - Jet grouting for ground water control contines at Pahemo Street and O A Street (#16, 18, 20, 22, 24, 2, and 4). |
|
| Friday, February 19, 2010 - Contractor setting forms for bell end of existing 42" RCP in Pit A1. |
|
| Friday, February 19, 2010 - 1st 16" PVC DR18 pipe is being installed at Pit A4 towards Pit A8. |
|
| Saturday, February 20, 2010 - Installation of new 16" PVC Sewerline "A" continues at Pit A4 towards Pit A8. |
|
| Saturday, February 20, 2010 - New 16" PVC Sewerline "A" from Pit A4 to Pit A8 completed. |
|
| Monday, February 22, 2010 - Jet grouting for ground water control at O’a Street, Sta. 0+00 to 0+25+ continues (#7, 9, 12, and 14). |
|
| Monday, February 22, 2010 - Restraining braces are being welded after the end of the annulus space is sealed with brick and mortar at Pit A4 for Sewerline "A" towards Pit A8. |
|
| Tuesday, February 23, 2010 - "Full Moon" view of new 16" PVC at Pit A4 towards Pit A8. |
|
| Tuesday, February 23, 2010 - Pit A3 end of ne 16" PVC from Pit A4 sealed and braced. |
|
| Wednesday, February 24, 2010 - Continues to form bell ends of existing 42" RCP in Pit A1. |
|
| Wednesday, February 24, 2010 - Concrete pour of bell ends of existing 42" RCP in progess (west and east side), in Pit A1. |
|
| Wednesday, February 24, 2010 - Finishing concrete for existing 42" RCP bell ends at Pit A1. |
|
| Wednesday, February 24, 2010 - Winch for pulling 16" PVC from Pit A2 is set up in Pit A3. |
|
| Thursday, February 25, 2010 - Installing new 16" PVC at Pit A2 towards Pit A3 using pulley system. |
|
| Thursday, February 25, 2010 - Forms being stripped at bell ends of existing 42" RCP in Pit A1. |
|
| Thursday, February 25, 2010 - Last pipe length with approximately 11.5' outside of casing at Pit A2 with 16" carrier pipe stopping 2' short in casing at Pit A3. |
|
| Thursday, February 25, 2010 - View of new 16" PVC sewerline at Pit A3 towards Pit A2. |
|
| Thursday, February 25, 2010 - "Full Moon" view of new 16" PVC from Pit A3 looking towards Pit A2. |
|
| Friday, February 26, 2010 - Excavation of pit floor for temporary support for existing 42" RCP continues in Pit A1. |
|