Community Planning & Engineering
Call: (808) 488-9955
|
|
| Monday, March 1, 2010 - Existing 42-inch reinforced concrete pipe is secured using support cradle and steel cables to trench I-beams. |
|
| Thursday, March 4, 2010 - Reinforcing steel and formwork for Sewer Manhole A1 is progress. |
|
| Friday, March 5, 2010 - Contractor continues to erect formwork and tie reinforcing steel for Sewer Manhole A1. |
|
| Saturday, March 6, 2010 - Concrete pour for Sewer Manhole "A1", mauka wall, in progress. |
|
| Wednesday, March 10, 2010 - Contractor installing T-Lok on inside of Sewer Manhole "A1" forms. |
|
| Thursday, March 11, 2010 - Contractor continues to tie reinforcing steel for Sewer Manhole "A1" at Pit A1. |
|
| Friday, March 12, 2010 - Contractor completing steel and formwork for Sewer Manhole "A1". |
|
| Saturday, March 13, 2010 - Concrete pour for Sewer Manhole "A1" walls in progress. |
|
| Saturday, March 13, 2010 - Contractor vibrating concrete for Sewer Manhole "A1" walls. |
|
| Tuesday, March 16, 2010 - Formwork for inside of Sewer Manhole "A1" is stripped, and T-Lok is cleaned prior to welding seams and joints. |
|
| Wednesday, March 17, 2010 - Contractor installing T-Lok weld strip over joints for Sewer Manhole "A1". |
|
| Thursday, March 18, 2010 - Concrete pour for channelized section of Sewer Manhole "A1" in progress. |
|
| Thursday, March 18, 2010 - Channelized section of Sewer Manhole "A1"for New 16-Inch PVC Sewerline Into Existing 42-Inch RCP. |
|
| Thursday, March 18, 2010 - Channelized section of Sewer Manhole "A1" for New 16-Inch PVC Sewerline Into Existing 42-Inch RCP completed. |
|
| Saturday, March 20, 2010 - Formwork for top of box section for Sewer Manhole "A1" in progress. |
|
| Monday, March 22, 2010 - Tying of reinforcing steel for deck of box section of Sewer Manhole "A1" in progress. |
|
| Tuesday, March 23, 2010 - Reinforcing steel and formwork for deck of box section of Sewer Manhole "A1" completed. |
|
| Tuesday, March 23, 2010 - Finishing of concrete for deck of box section of Sewer Manhole "A1" in progress. |
|
| Wednesday, March 24, 2010 - Stripping formwork of box section for Sewer Manhole "A1". |
|
| Wednesday, March 31, 2010 - Stripping formwork for top deck of box section progress. |
|
| Wednesday, March 3, 2010 - Potholing (probing) for existing water lateral at Lii Ipo Street, Sta. 2+20+ continues. |
|
| Friday, March 5, 2010 - Potholing (probing) for existing fire hydrant lines at Lokowai Street, Sta. 2+75+, and Sta 5+25+. |
|
| Monday, March 8, 2010 - Probing for existing drain lines, and sewer lateral at Lokowai Street, Sta. 2+25+. |
|
| Thursday, March 11, 2010 - Potholing (probing) for existing water main at Pahemo Street, Sta. 0+30+ in progress. |
|
| Thursday, March 11, 2010 - Potholing (probing) for existing sewer lateral at Lokowai Street, Sta. 4+75+ in progress. |
|
| Monday, March 15, 2010 - Potholing (probing) for sewer lateral at Lii Ipo Street, Sta. 4+15+, Mauka. |
|
| Monday, March 15, 2010 - Potholing (probing) for sewer lateral at Lii Ipo Street, Sta. 3+90+, Makai. |
|
| Tuesday, March 16, 2010 - Potholing (probing) for sewer lateral at Lii Ipo Street, Sta. 3+00+, Mauka. |
|
| Tuesday, March 16, 2010 - Potholing (probing) for sewer lateral at Lii Ipo Street, Sta 6+25+, and Sta 6+55+. |
|
| Wednesday, March 17, 2010 - Potholing (probing) for sewer lateral at Pahemo Street, Sta 1+25+, Mauka and Makai. |
|
| Wednesday, March 17, 2010 - Potholing (probing) for existing 10-inch sewer main at Pahemo Street, Sta. 3+50+. |
|
| Wednesday, March 17, 2010 - Potholing (probing) for existing 10-inch sewer main at Pahemo Street, Sta. 3+35+. |
|
| Wednesday, March 17, 2010 - Potholing (probing) for existing sewer lateral at Lii Ipo Street, Sta. 0+75+. |
|
| Thursday, March 18, 2010 - Potholing (probing) for existing sewer jackets and gas line at Kanuku Street, Sewer Manhole C4. |
|
| Thursday, March 18, 2010 - Potholing (probing) for existing sewer lateral at Lokowai Street, Sta. 4+42+, and Sta. 5+80+. |
|
| Friday, March 19, 2010 - Potholing (probing) for existing sewer lateral at Lokowai Street, Sta 4+91+, and Sta. 6+25+. |
|
| Monday, March 22, 2010 - Potholing (probing) for existing sewer lateral at Olepe Loop, Sta. 2+57+, Sta. 1+95+, and Sta. 0+86. |
|
| Monday, March 22, 2010 - Potholing (probing) of existing sewer line at Lii Ipo Street, Sta. 7+48+ in progress. |
|
| Monday, March 22, 2010 - Potholing (probing) of existing sewer line at Lii Ipo Street, Sta. 8+69+ in progress. |
|
| Tuesday, March 23, 2010 - Potholing (probing) for existing sewer lateral at Olepe Loop, Sta. 0+21+, Sta. 1+25+, and Sta. 1+76+. |
|
| Wednesday, March 24, 2010 - Contractor continues to pothole for existing sewer lateral at Olepe Loop, Sta. 2+00. |
|
| Wednesday, March 24, 2010 - Potholing for sewer lateral, sewer main, and water lateral, at Lii Ipo Street, Sta. 0+50+, and Sta. 2+15 continues. |
|
| Thursday, March 25, 2010 - Contractor probing for existing water main at Lii Ipo Street, Sta. 2+20+. |
|
| Monday, March 29, 2010 - Potholing/probing for existing water and sewer mains at Lokowai Street in progress. |
|
| Monday, March 29, 2010 - Probed existing water main by Pit F3, Olepe Loop, Sta. 1+50+. |
|
| Monday, March 29, 2010 - Probed for esisting sewer main at Olepe Street, Sta. 0+65+. |
|
| Monday, March 29, 2010 - Probed existing 8" water main crossing at Lii Ipo Street, Sta. 8+60+. |
|
| Wednesday, March 31, 2010 - Potholing/probing for abandoned 8-inch water main at Lii Ipo Street, Sta. 3+25+. |
|
| Wednesday, March 10, 2010 - Sewer lateral relocation work at Lokowai Street, Sta. 2+25+ in progress. |
|
| Wednesday, March 10, 2010 - Sewer lateral relocation work at Lokowai Street, Sta. 2+25+ continues. |
|
| Thursday, March 25, 2010 - Relocating existing water lateral at Lii Ipo, Sta. 2+20+, for Sewerline "J" Sewer Manhole. |
|
| Thursday, March 25, 2010 - Excavating existing water lateral at Lii Ipo, Sta. 2+15+. |
|
| Thursday, March 25, 2010 - Relocation of existing water lateral to clear new SMH for Sewerline "J" at Lii Ipo Street, Sta. 2+20+. |
|
| Monday, March 29, 2010 - Installing new 6" PVC sewer lateral at Lii Ipo Street, Sta. 8+15+. |
|
| Monday, March 29, 2010 - Leveling 3B fine at Lii Ipo Street, Sta. 8+18+ to Sta. 8+89+. |
|
| Tuesday, March 30, 2010 - Sewerline "J" installation at Lii Ipo Street in progress. |
|
| Wednesday, March 31, 2010 - Controlled Low Strength Material concrete is poured for Sewerline "J" at Lii Ipo Street, Sta. 7+80+ to Sta. 8+90+. |
|
| Monday, March 15, 2010 - Preparing lightweight conrete fill for annulus grouting from Pit A4 to Pit A8, Sewerline "A". |
|
| Monday, March 22, 2010 - Annulus grouting from Pit A2 to Pit A3 in progress. |
|
| Monday, March 22, 2010 - Annulus grouting overflow piping at Pit A3. |
|
| Monday, March 22, 2010 - Entry point of lightweight concrete at Pit A2 for annulus grouting torwards Pit A3. |
|
| Monday, March 1, 2010 - Jet grouting for Sewer Manhole "K2" at Pahemo Street for ground water control in progress. |
|
| Monday, March 8, 2010 - Jet grouting for Sewer Manhole "K2" at Pahemo Street for ground water control continues. |
|
| Wednesday, March 10, 2010 - Jet grouting for Sewer Manhole "K1" for ground water control in progress. |
|
| Monday, March 15, 2010 - Jet grouting for Waterline "F" ground water control in progress. |
|
| Tuesday, March 16, 2010 - Jet grouting for Sewer Manhole C2 on Lokowai Street for ground water control in progress. |
|
| Wednesday, March 17, 2010 - Jet grouting for Sewer Manhole C2 on Lokowai Street for ground water control in progress. |
|
| Friday, March 19, 2010 - Jet grouting for Sewer Manhole C1 on Lokowai Street in progress. |
|
| Tuesday, March 23, 2010 - Jet grouting ground water control for Waterline "F" on Pahemo Street continues. |
|
| Wednesday, March 24 - 26, 2010 - Jet grouting ground water control for Waterline "F" on Pahemo Street continues. |
|
| Friday, March 26, 2010 - Jet grouting for Pit C1 ground water control at Lokowai Street in progress. |
|
| March 25 - 31, 2010 - Jet grouting for ground water control for Sewerline "K" between K5 and K6 at Kanuku Street in progress. |
|
| Monday, March 29, 2010 - Jet grouting for Pit C4 ground water control continues at Kanuku Street. |
|
| March 30 - 31, 2010 - Jet grouting for ground water control for Sewerline "K" between Pit K5 and Pit K6 in progress. |
|