CONSTRUCTION ACTIVITIES, PHOTOS AND SCHEDULE

March 2010

Progress Schedule as of March 5, 2010

Progress Schedule 1 as of March 16, 2010
Progress Schedule 2 as of March 16, 2010


Construction Activities as of March 5, 2010

  1. BASIC BID WORK ITEMS



    • Jet Grouting

      • Hekaha Street.
      • Pit A2 to Pit A3 completed October 31, 2009 - Jet grouted Sewerline
        "A" alignment pipe support.
      • Pit A2 to Pit A1 completed November 5, 2010 - Jet grouted Sewerline
        "A" alignment pipe support.
      • Pit A3 to Pit A4 completed January 16, 2010 - Sewerline "A"
        alignment pipe support (end of Basic Bid, Hekaha Street,
        Sta. 6+38+).
      • Pit A4 to Pit A8 completed January 18, 2010 - Sewerline "A"
        alignment pipe support.
      • Kanuku Street
      • Jet grouting for water control for Sewerline "K" completed
        February 9, 2010.
      • Pahemo Street
      • Jet grouting for water control for Sewerline "K", January 26,
        2010 to February 16, 2010.
      • O'a Street
      • Jet grouting for water control for Sewerline "K1", February 17,
        2010 - February 19, 2010.


    • Jet Grout Test Program

      • Completed January 11, 2010 - Second (Final) Required Test Program.


    • Receiving Pit Shaft A1 (Pit A1)

      • Completed January 11, 2010.


    • Jacking/Receiving Shaft A2 (Pit A2)

      • Completed November 15, 2009.


    • Receiving Shaft A3 (Pit A3)

      • Completed November 19, 2010.


    • Jacking/Receiving Shaft A4 (Pit 4 – VE, Additive Alternate No. 1)

      • Completed January 14, 2010.


    • Receiving Shaft A8 (Pit A8 – VECP, Additive Alternate No. 1)

      • Completed February 4, 2010.


    • Microtunneling & Steel Casing

      • Pit A2 to Pit A3 completed November 21, 2009.
      • Pit A2 to Pit A1 completed December 16, 2010.
      • Pit A4 to Pit A3 completed February 1, 2010.
      • Pit A4 to Pit A8 completed February 13, 2010.


    • PVC Pipe

      • Pipe installation work from Pit A2 to Pit A1 completed January 15, 3020.
      • Grouting of annulus space with lightweight concrete
        completed January 9, 2010.
      • Hydrotest completed January 11, 2010.
      • Pipe installation work from Pit A4 to Pit A3 completed February 3,
        2010 (Basic Bid ends at Sta. 6+38+, Hekaha Street).
      • Pipe installation work from Pit A2 to Pit A3 completed
        February 25, 2010.
      • Pipe installation work from Pit A4 to Pit A8 completed on
        February 20, 2010.


    • SMH No. 1

      • Excavate below existing 42" RCP for contruction of lateral support.
      • Existing Utility Relocation.
      • Sewer by-pass line on Pahemo Street completed February 12, 2010.
      • New 6" sewer lateral on Pahemo Street installed February 19, 2010.
      • Prepare Sewer manhole for removal on Pahemo Street,
        Sta. 2+15+, February 9, 2010.
      • Inclinometer.
      • Installed inclinometer casing adjacent to Pit A8 on February 1, 2010.


    • Inclinometer

      • Installed inclinometer casing adjacent to Pit A4 (Jan. 5, 2010).




Photos of March 2010 Construction Activities

Monday, March 1, 2010 - Existing 42-inch reinforced concrete pipe is secured using support cradle and steel cables to trench I-beams.
Thursday, March 4, 2010 - Reinforcing steel and formwork for Sewer Manhole A1 is progress.
Friday, March 5, 2010 - Contractor continues to erect formwork and tie reinforcing steel for Sewer Manhole A1.
Saturday, March 6, 2010 - Concrete pour for Sewer Manhole "A1", mauka wall, in progress.
Wednesday, March 10, 2010 - Contractor installing T-Lok on inside of Sewer Manhole "A1" forms.
Thursday, March 11, 2010 - Contractor continues to tie reinforcing steel for Sewer Manhole "A1" at Pit A1.
Friday, March 12, 2010 - Contractor completing steel and formwork for Sewer Manhole "A1".
Saturday, March 13, 2010 - Concrete pour for Sewer Manhole "A1" walls in progress.
Saturday, March 13, 2010 - Contractor vibrating concrete for Sewer Manhole "A1" walls.
Tuesday, March 16, 2010 - Formwork for inside of Sewer Manhole "A1" is stripped, and T-Lok is cleaned prior to welding seams and joints.
Wednesday, March 17, 2010 - Contractor installing T-Lok weld strip over joints for Sewer Manhole "A1".
Thursday, March 18, 2010 - Concrete pour for channelized section of Sewer Manhole "A1" in progress.
Thursday, March 18, 2010 - Channelized section of Sewer Manhole "A1"for New 16-Inch PVC Sewerline Into Existing 42-Inch RCP.
Thursday, March 18, 2010 - Channelized section of Sewer Manhole "A1" for New 16-Inch PVC Sewerline Into Existing 42-Inch RCP completed.
Saturday, March 20, 2010 - Formwork for top of box section for Sewer Manhole "A1" in progress.
Monday, March 22, 2010 - Tying of reinforcing steel for deck of box section of Sewer Manhole "A1" in progress.
Tuesday, March 23, 2010 - Reinforcing steel and formwork for deck of box section of Sewer Manhole "A1" completed.
Tuesday, March 23, 2010 - Finishing of concrete for deck of box section of Sewer Manhole "A1" in progress.
Wednesday, March 24, 2010 - Stripping formwork of box section for Sewer Manhole "A1".
Wednesday, March 31, 2010 - Stripping formwork for top deck of box section progress.
Wednesday, March 3, 2010 - Potholing (probing) for existing water lateral at Lii Ipo Street, Sta. 2+20+ continues.
Friday, March 5, 2010 - Potholing (probing) for existing fire hydrant lines at Lokowai Street, Sta. 2+75+, and Sta 5+25+.
Monday, March 8, 2010 - Probing for existing drain lines, and sewer lateral at Lokowai Street, Sta. 2+25+.
Thursday, March 11, 2010 - Potholing (probing) for existing water main at Pahemo Street, Sta. 0+30+ in progress.
Thursday, March 11, 2010 - Potholing (probing) for existing sewer lateral at Lokowai Street, Sta. 4+75+ in progress.
Monday, March 15, 2010 - Potholing (probing) for sewer lateral at Lii Ipo Street, Sta. 4+15+, Mauka.
Monday, March 15, 2010 - Potholing (probing) for sewer lateral at Lii Ipo Street, Sta. 3+90+, Makai.
Tuesday, March 16, 2010 - Potholing (probing) for sewer lateral at Lii Ipo Street, Sta. 3+00+, Mauka.
Tuesday, March 16, 2010 - Potholing (probing) for sewer lateral at Lii Ipo Street, Sta 6+25+, and Sta 6+55+.
Wednesday, March 17, 2010 - Potholing (probing) for sewer lateral at Pahemo Street, Sta 1+25+, Mauka and Makai.
Wednesday, March 17, 2010 - Potholing (probing) for existing 10-inch sewer main at Pahemo Street, Sta. 3+50+.
Wednesday, March 17, 2010 - Potholing (probing) for existing 10-inch sewer main at Pahemo Street, Sta. 3+35+.
Wednesday, March 17, 2010 - Potholing (probing) for existing sewer lateral at Lii Ipo Street, Sta. 0+75+.
Thursday, March 18, 2010 - Potholing (probing) for existing sewer jackets and gas line at Kanuku Street, Sewer Manhole C4.
Thursday, March 18, 2010 - Potholing (probing) for existing sewer lateral at Lokowai Street, Sta. 4+42+, and Sta. 5+80+.
Friday, March 19, 2010 - Potholing (probing) for existing sewer lateral at Lokowai Street, Sta 4+91+, and Sta. 6+25+.
Monday, March 22, 2010 - Potholing (probing) for existing sewer lateral at Olepe Loop, Sta. 2+57+, Sta. 1+95+, and Sta. 0+86.
Monday, March 22, 2010 - Potholing (probing) of existing sewer line at Lii Ipo Street, Sta. 7+48+ in progress.
Monday, March 22, 2010 - Potholing (probing) of existing sewer line at Lii Ipo Street, Sta. 8+69+ in progress.
Tuesday, March 23, 2010 - Potholing (probing) for existing sewer lateral at Olepe Loop, Sta. 0+21+, Sta. 1+25+, and Sta. 1+76+.
Wednesday, March 24, 2010 - Contractor continues to pothole for existing sewer lateral at Olepe Loop, Sta. 2+00.
Wednesday, March 24, 2010 - Potholing for sewer lateral, sewer main, and water lateral, at Lii Ipo Street, Sta. 0+50+, and Sta. 2+15 continues.
Thursday, March 25, 2010 - Contractor probing for existing water main at Lii Ipo Street, Sta. 2+20+.
Monday, March 29, 2010 - Potholing/probing for existing water and sewer mains at Lokowai Street in progress.
Monday, March 29, 2010 - Probed existing water main by Pit F3, Olepe Loop, Sta. 1+50+.
Monday, March 29, 2010 - Probed for esisting sewer main at Olepe Street, Sta. 0+65+.
Monday, March 29, 2010 - Probed existing 8" water main crossing at Lii Ipo Street, Sta. 8+60+.
Wednesday, March 31, 2010 - Potholing/probing for abandoned 8-inch water main at Lii Ipo Street, Sta. 3+25+.
Wednesday, March 10, 2010 - Sewer lateral relocation work at Lokowai Street, Sta. 2+25+ in progress.
Wednesday, March 10, 2010 - Sewer lateral relocation work at Lokowai Street, Sta. 2+25+ continues.
Thursday, March 25, 2010 - Relocating existing water lateral at Lii Ipo, Sta. 2+20+, for Sewerline "J" Sewer Manhole.
Thursday, March 25, 2010 - Excavating existing water lateral at Lii Ipo, Sta. 2+15+.
Thursday, March 25, 2010 - Relocation of existing water lateral to clear new SMH for Sewerline "J" at Lii Ipo Street, Sta. 2+20+.
Monday, March 29, 2010 - Installing new 6" PVC sewer lateral at Lii Ipo Street, Sta. 8+15+.
Monday, March 29, 2010 - Leveling 3B fine at Lii Ipo Street, Sta. 8+18+ to Sta. 8+89+.
Tuesday, March 30, 2010 - Sewerline "J" installation at Lii Ipo Street in progress.
Wednesday, March 31, 2010 - Controlled Low Strength Material concrete is poured for Sewerline "J" at Lii Ipo Street, Sta. 7+80+ to Sta. 8+90+.
Monday, March 15, 2010 - Preparing lightweight conrete fill for annulus grouting from Pit A4 to Pit A8, Sewerline "A".
Monday, March 22, 2010 - Annulus grouting from Pit A2 to Pit A3 in progress.
Monday, March 22, 2010 - Annulus grouting overflow piping at Pit A3.
Monday, March 22, 2010 - Entry point of lightweight concrete at Pit A2 for annulus grouting torwards Pit A3.
Monday, March 1, 2010 - Jet grouting for Sewer Manhole "K2" at Pahemo Street for ground water control in progress.
Monday, March 8, 2010 - Jet grouting for Sewer Manhole "K2" at Pahemo Street for ground water control continues.
Wednesday, March 10, 2010 - Jet grouting for Sewer Manhole "K1" for ground water control in progress.
Monday, March 15, 2010 - Jet grouting for Waterline "F" ground water control in progress.
Tuesday, March 16, 2010 - Jet grouting for Sewer Manhole C2 on Lokowai Street for ground water control in progress.
Wednesday, March 17, 2010 - Jet grouting for Sewer Manhole C2 on Lokowai Street for ground water control in progress.
Friday, March 19, 2010 - Jet grouting for Sewer Manhole C1 on Lokowai Street in progress.
Tuesday, March 23, 2010 - Jet grouting ground water control for Waterline "F" on Pahemo Street continues.
Wednesday, March 24 - 26, 2010 - Jet grouting ground water control for Waterline "F" on Pahemo Street continues.
Friday, March 26, 2010 - Jet grouting for Pit C1 ground water control at Lokowai Street in progress.
March 25 - 31, 2010 - Jet grouting for ground water control for Sewerline "K" between K5 and K6 at Kanuku Street in progress.
Monday, March 29, 2010 - Jet grouting for Pit C4 ground water control continues at Kanuku Street.
March 30 - 31, 2010 - Jet grouting for ground water control for Sewerline "K" between Pit K5 and Pit K6 in progress.