CONSTRUCTION ACTIVITIES, PHOTOS AND SCHEDULE

April 2010

Progress Schedule as of April 15, 2010

Progress Schedule 1 as of April 15, 2010


Construction Activities as of April 15, 2010

  1. BASIC BID WORK ITEMS



    • Jet Grouting

      • Pahemo Street.
      • Pit for SMH K1 (March 2 - 11, 2010).
      • Pit for SMH K2 (Feb. 25, 2010 - March 3, 2010).
      • Waterline "F" (March 4 - 25, 2010).
      • SMH K5 to SMH K6 (March 9 - 16, 2010).
      • O'a Street
      • Lokowai Street
      • Pit C1, Pit C2 and C3 (March 16 - 25, 2010).
      • Waterline "A" (March 29 - April 3, 2010).
      • Lii Ipo Street
      • Pit "J3" (March 29 - April 3, 2010).


    • PVC Pipe - N/A for Month of March, 2010



    • Annulus Pipe Grouting

      • Pit A4 to Pit A8 (March 4, 2010).
      • Pit A4 to Pit A8 (March 4, 2010).
      • Pit A2 to Pit A3 (March 23 - 24, 2010).


    • SMH No. 1

      • SMH A1 (Feb. 23 - April 15, 2010).


    • Potholing

      • Olepe Loop, Pahemho Street, Lii Ipo Street, and Lokowai Street
        (March 1 - 31, 2010).


    • Existing Utility Relocation - N/A for month of March, 2010



    • Open Cut Sewerline Installation

      • Lii Ipo Street.
      • Sewerline "J" (March 15 - 23, 2010).
      • O'a Street .
      • Sewerline "K1" (March 22 - 29, 2010).


Photos of April 2010 Construction Activities

Thursday, April 1, 2010 - Crew continues to jet grout for groundwater control for Sewerline "K", between Sewer Manhole "K5" and Sewer Manhole "K6".
Thursday, April 1, 2010 - Plant inspection of 48-inch diameter cone in progress. T-Lock and welded wire mesh are placed prior to completing exterior formwork.
Thursday, April 1, 2010 - Plant inspection of 48-inch diameter riser in progress. T-Lock and welded wire mesh are placed prior to completing exterior formwork.
Thursday, April 1, 2010 - Plant inspection of 72-inch diameter riser in progress. T-Lock and welded wire mesh are placed prior to completing exterior formwork.
Thursday, April 1, 2010 - Plant inspection of 48-inch diameter riser in progress. Concrete pour in progress.
Thursday, April 1, 2010 - Jet grouting for Pit "C4" ground water control in progress.
Thursday, April 1, 2010 - Potholing/probing for abandoned waterline at Lii Ipo Street, Sta. 4+22+ in progress.
Thursday, April 1, 2010 - Locating an existing sewerline at Pahemo Street, Sta. 0+02+ in preparation for installing Sewerline "K1".
Thursday, April 1, 2010 - Locating an existing sewerline at Pahemo Street, Sta. 0+40+ in preparation for installing Sewerline "K1".
Thursday, April 1, 2010 - Potholing/probing for abandoned waterline at Lii Ipo Street, Sta. 3+80+.
Thursday, April 1, 2010 - Installation of Sewerline "G3" at Pahemo Street, Sta. 2+08+ in progess.
Friday, April 2, 2010 - Contractor laying out jet grouting columns for Pit "J3" at Lii Ipo Street.
Friday, April 2, 2010 - Contractor re-welding loose steel plates covering Shaft "A8" near the intersection of Hekaha St., and Pahemo St., also at Pahemo St. and Oa St. intersection.
Friday - Tuesday, April 2 - 6, 2010 - Jet grouting Pit "J3" for ground water control at Lii Ipo Street in progress.
Saturday - Monday, April 3 - 5, 2010 - Jet grouting Pit "C4" at Kanuku Street for groundwater control continues.
Monday, April 5, 2010 - Contractor removing abandoned 8-inch watermain at Pit "J2", Lii Ipo Street, Sta. 4+65+ to Sta. 4+75+.
Monday, April 5, 2010 - Contractor saw cutting/excavating concrete driveway for removal of abandoned 8-inch water main at Lii Ipo Street, Sta. 3+96+ to Sta. 4+18+.
Monday - Tuesday, April 5 - 6, 2010 - Contractor excavating concrete driveway for removal of abandoned 8-inch water main at Lii Ipo Street, Sta. 3+96+ to Sta. 4+20+.
Monday, April 5, 2010 - Contractor installing new 8-inch PVC, Sewerline "K1" at Oa Street, Sta. 0+00+ to Sta. 0+30+.
Monday, April 5, 2010 - Backfilling trench with 3B rock after removal of 8-inch watermain, Pit "J2", at Lii Ipo Street, Sta. 4+65+ to Sta. 4+75+.
Tuesday, April 6, 2010 - Formwork for reinforced concrete jacket for Sewerline "K1" at Oa Street, Sta. 0+00+ to Sta. 0+10+ completed; concrete pour in progress.
Tuesday, April 6, 2010 - Contractor laid out jet grout column locations for Pit "F5", Lokowai Street, Sta. 4+95+.
Wednesday, April 7, 2010 - Relocation of existing sewer main at Lii Ipo Street, from Sta. 4+75+ to Sta. 4+50+ in progress.
Wednesday, April 7, 2010 - Receiving Pit "K1" excavation at Pahemo Street in progress.
Wednesday, April 7, 2010 - Installing "cans shoring support" for receiving Pit "K1" at Pahemo Street in progress.
Wednesday, April 7, 2010 - Backfilling of relocated sewerline at Lii Ipo Street, from Sta. 4+75+ to Sta. 4+50+ in progress.
Thursday, April 8, 2010 - Jet grouting Pit "K5" for ground water control at Lokowai Street in progress.
Thursday, April 8, 2010 - Conractor placing 3B rock in filter fabric over CLSM prior to lightweight concrete backfill for Sewerline "K1", Oa St., Sta. 0+00+ to Sta. 0+30+.
Thursday, April 8, 2010 - Pouring lightweight concrete backfill for Sewerline "K1", Oa St., Sta. 0+00+ to Sta. 0+30+ in progress.
Thursday, April 8, 2010 - Relocation of existing 8-inch sewer main at Lokowai Street, Sta. 3+80+, and Sta. 4+20+ in progress.
Thursday, April 8, 2010 - First section of receiving "can" for Pit "C1" at Lokowai Street is being lowered into place.
Thursday - Friday, April 8 - 9, 2010 - Jet grouting Pit "J2" in progress.
Thursday, April 8, 2010 - Cement trucks at Hekaha Street, near the Waimalu Shopping Center, has its load mixed with foaming agent for lightweight concrete backfilling of Shaft "A1".
Thursday, April 8, 2010 - Second of 6-foot high lighweight concrete backfill for Shaft "A1" completed.
Friday, April 9, 2010 - Backfiling new 8-inch Sewerline "K1" at Oa Street, from Sta. 0+00+ to Sta. 0+30+ in progress.
Friday, April 9, 2010 - Jet grouting for Pit "F5" at Pahemo Street continues.
Friday, April 9, 2010 - Sewer Manhole No. A1 wall section is being sealed at cold joint.
Friday, April 9, 2010 - Contractor backfilling trench with base course at Lii Ipo Street, Sta. 7+89+ to Sta. 8+14+.
Saturday, April 10, 2010 - Contractor completed the layout of jet grout columns for Pit "F3" at Olepe Loop.
Saturday, April 10, 2010 - Lightweight concrete backfill pour for Shaft "A1" for 3rd lift I progress.
Saturday, April 10, 2010 - Jet grouting for Pit "F3" at Olepe Loop continues.
Monday, April 12, 2010 - Placing receiving "can" into place for Pit "C2".
Monday, April 12, 2010 - Relocating existing 10-inch sewer main for new Pit "F4" sewermanhole, near Lokowai Street and Pahemo Street Intersection, Sta. 4+20+.
Monday, April 12, 2010 - Excavation for receiving "can" for Pit "F5" at Lokowai Street in progress.
Tuesday, April 13, 2010 - Excavation for Pit "J3" receiving "can", and removal of abandoned 8-inch water main in progress.
Tuesday, April 13, 2010 - Receiving "can" installation for Pit "J3" in progress.
Tuesday - Friday, April 13 - 16, 2010 - Contractor starts with jet grouting of Pit "J1" at Lii Ipo Street.
Tuesday, April 13, 2010 - Jet grouting of Pit "J2" at Lii Ipo Street 50% completed.
Tuesday - Friday, April 13 - 16, 2010 - Contractor installing temporary bypass of existing 10-inch sewerline and 8-inch sewerline around SMH No. 599629 at intersection of Olepe Lp., Pahemo St. & Lokowai St.
Tuesday - Friday, April 13 - 16, 2010 - Contractor installing temporary bypass of existing 10-inch sewerline and 8-inch sewerline around SMH No. 599629 at intersection of Olepe Lp., Pahemo St. &
Thursday - Friday, April 15 - 16, 2010 - Waterline "F" relocation at Pahemo Street, Sta. 0+00+ to Sta. 0+41+ in progress.
Thursday, April 15, 2010 - Jet grouting for Pit "F2" in progress.
Thursday - Monday, April 15 - 19, 2010 - Waterline "F" relocation at Pahemo Street, Sta. 0+00+ to Sta. 0+41+ ; tying reinforcing steel for concrete jacket in progress.
Saturday, April l17, 2010 - Jet grouting for Pit "J2" at Lii Ipo Street, Sta. 4+70+ in progress.
Saturday - Monday, April l17 - 19, 2010 - Jet grouting for Pit "F2" at Olepe Loop continues.
Monday, April 19, 2010 - Waterline "F" relocation at Pahemo Street, Sta. 0+00+ to Sta. 0+41+ ; vibrating concrete for top vertical bend.
Tuesday - Wednesday, April 20 - 21, 2010 - Jet grouting Pit "F1" at Olepe Loop in progress.
Tuesday, April 20, 2010 - Probing for existing 24-inch drain (west side) in progress.
Tuesday, April 20, 2010 - Probing for existing 24-inch drain (west side) in progress.
Tuesday, April 20, 2010 - Bracing/shoring existing 24-inch drain (west side) in progress.
Tuesday, April 20, 2010 - Reconnection of of 24-inch drainline, electrical and telephone conduits and to be re-aligned to original location at Shaft "A1".
Wednesday, April 21, 2010 - Contractor demolished SMH No. 599629 at intersection of Olepe Lp., Pahemo St. & Lokowai St.
Wednesday - Monday, April 21 - 26, 2010 - Jet grouting for groundwater control for Sewerline "K" between Pits "K5" and "K6" on Kanuku Street continues.
Wednesday - Friday, April 21 - 23, 2010 - Jet grouting of Pit "I2" at Olepe Loop in progress.
Wednesday, April 21, 2010 - Potholing/probing for existing 6-inch sewer lateral at Pahemo Street, Sta. 5+28+ in progress.
Wednesday - Friday, April 21 - 23, 2010 - Temporary sewer bypass of existing 6-inch sewer lateral at Sewerline "G4", Sewer Manhole "G4" nearly completed.
Friday, April 23, 2010 - Temporary sewer bypass of existing 6-inch sewer lateral at Sewerline "G4", Sewer Manhole "G4" nearly completed.
Saturday, April 24, 2010 - Jet grouting for Pit "F4" at Pahemo Street and Lokowai Street intersection continues.
Saturday - Monday, April 24 - 26, 2010 - Jet grouting for Pit "G1" in progress.
Monday, April 26, 2010 - Potholing for existing 8-inch waterline for new Waterline "D" installation at Pahemo Street, Sta. 0+80+.
Monday, April 26, 2010 - Removal of an abandoned waterline in conflict with Pit "G4" on Pahemo Street is underway.
Monday, April 26, 2010 - Contractor placed rock berm in preparation for jet grouting of Pit "F4" located near Pahemo Street and Lokowai Street intersection.
Monday, April 26, 2010 - Contractor constructed Sewer Manhole "A1" cone at Pit "A1", corner of Hekaha Street, and Kamehameha Highway.
Tuesday - Wednesday, April 27 - 28, 2010 - Jet grouting for Pit "F4" near Pahemo Street and Lokowai Street continues.
Tuesday, April 27, 2010 - Excavating Pit "J1" at Lii Ipo Street, Sta. 2+20+ to install receiving "can".
Wednesday - Friday, April 28 - 30, 2010 - Jet grouting for Pit "G4" at Pahemo Street continues.
Wednesday, April 28, 2010 - Potholing for existing water lateral at Pahemo Street, Sta. 7+55+ in progress.
Wednesday, April 28, 2010 - Potholing for existing sewer lateral at Pahemo Street, Sta. 7+74+ in progress.
Wednesday, April 28, 2010 - Jet grouting for Sewerline "K" at Kanuku Street continues.
Wednesday, April 28, 2010 - Potholing for existing sewer lateral at Pahemo Street, Sta. 8+40+ in progress.
Wednesday, April 28, 2010 - Contractor poured lightweight concrete backfill for 24-inch drainline at Ewa side of Pit "A1".
Thursday, April 29, 2010 - Installation of new Waterline "D" at Pahemo Street continues.
Thursday - Friday, April 29 - 30, 2010 - Jet grouting for Sewerline "K" ground water control at Kanuku Street, between Pit "K5" and Pit "K6" continues.
Thursday, April 29, 2010 - Installation of temporary sewer bypass system for existing 8-inch sewer lateral in progress at Kanuku Street, Sta. 2+27+, Sewerline "D".
Thursday, April 29, 2010 - Backfilling temporary sewer bypass system trench for existing 8-inch sewer lateral in progress at Kanuku Street, Sta. 2+27+, Sewerline "D".
Friday, April 30, 2010 - Potholing existing 6-inch sewer lateral at Kanuku Street, Sta. 1+69+ in progress.
Friday, April 30, 2010 - Potholing existing 6-inch sewer lateral at Lokowai Street, Sta. 9+04+ in progress.
Friday, April 30, 2010 - Jet grouting Pit "F4" at Pahemo Street continues.
Friday, April 30, 2010 - Controlled Low Strength Material (CLSM) pour for new Waterline "D" at Pahemo Street, WL "D" Sta. 0+00+ to Sta. 0+12+, and WL "D" Sta. 0+41+.