| June 1, 2010 - Sewerline "A1" jet grouting for groundwater control begins. |
|
| June 1,2010 - Tunneling under existing 24-inch drain line for new fire hydrant lateral, Waterline "E" at Lii Ipo Street. |
|
| June 1, 2010 - Construction of new fire hydrant lateral at Lokowai Street, Sta. 5+35+. |
|
| June 2, 2010 - Concrete reaction block for "tee" of new fire hydrant lateral at Lokowai Street, Sta. 7+51+. |
|
| June 3, 2010 - Relocation of existing 8-inch Waterline "D" at Pahemo Street. |
|
| June 3, 2010 - Setting up GBM at Pit A3 on Hekaha Street for pilot tube operation towards Pit C1 at Lokowai Street. |
|
| June 3, 2010 - Pressure testing tapping tee assembly prior to performing a live tap for new fire hydrant lateral at Lokowai Street, Sta. 2+43+. |
|
| June 1, 2010 - Jet grouting for ground water control for open cut sewer main connection at Pit A2, Hekaha Street. |
|
| June 1, 2010 - Additional bracing at Pit C1 to free up auger casings. |
|
| June 2, 2010 - Contractor using three hydraulic rams to push auger casings back to Pit A1 from Pit C1 at Lokowai Street. |
|
| June 4, 2010 - Pushing 15" Permalock steel casings from Pit A3, Hekaha Street, towards Pit C1 at Lokowai Street. |
|
| June 4, 2010 - Removal of auger casings from Pit C1, Lokowai Street, in progress. |
|
| June 4, 2010 - Re-setting GBM at Pit A3, towards SMH F1, Lokowai Street in progress. |
|
| June 7, 2010 - Contractor installing Waterline "D", 8-inch D.I. pipe. |
|
| June 9, 2010 - Demolition and removal of pipe jack concrete block support in progress. |
|
| June 7, 2010 - Pilot tube boring from Pit A3, Hekaha Street, to SMH F5, Lokowai Street. |
|
| June 8, 2010 - Lowering augers wit steel casing in place at Pit A3 towards SMH F5. |
|
| June 8, 2010 - Removal of concrete block at Pit A2 in progress. |
|
| June 9, 2010 - Micrometer reading of Permalock steel casing bell end. |
|
| June 9, 2010 - Pushing Permalock steel casings from Pit A3, Hekaha Street, to SMH F5, Lokowai Street. |
|
| June 10, 2010 - Setting up GBM in Pit A4, Hekaha Street. |
|
| June 14, 2010 - SMH A2 pre-cast floor and riser delivered on site. |
|
| June 14, 2010 - Construction of fire hydrant curb guard at Lokowai Street, Sta. 5+35+ in progress. |
|
| June 14, 2010 - Reconstruction of curb return area fronting Cutter Ford continues. |
|
| June 17, 2010 - Cold planing and A.C. paving of jet grouted area, Hekaha Street, Sta. 1+40+ to Sta. 2+85+. |
|
| June 18, 2010 - Precast SMH installed at Pit A2, and 16-inch PVC carrier pipe extended. |
|
| June 14, 2010 - Setting up GBM in Pit A4 towards SMH J1. |
|
| June 14, 2010 - Pilot tube operation from Pit A4 to Pit J1 in progress. |
|
| June 18, 2010 - Waterline "D" installation at Pahemo Street continues. |
|
| June 18, 2010 - Removal of GBM from Pit A4 to set up at Pit A8. |
|
| June 19, 2010 - Setting up GBM equipment in Pit A8, Hekaha Street. |
|
| June 21, 2010 - Contractor preparing to channel the floor of New SMH A2, Hekaha Street. |
|
| June 22, 2010 - Formwork for reinforced concrete pad for gate valve frame and cover for Waterline "E", Lii Ipo Street. |
|
| June 22, 2010 - Installing new 10" PVC sewerline from Pit A3, Hekaha Street, to Pit F5 on Lokowai Street. |
|
| June 22, 2010 - Reinforcing steel, T-Lock for SMH A2 riser section at Hawaii Concrete Products. |
|
| June 23, 2010 - A.C. pavement restoration for Waterline "E", and at Sta. 6+29+, Lii Ipo Street. |
|
| June 23, 2010 - Completed installation of new 10" PVC sewerline from Pit A3, Hekaha Street, to Pit F5 on Lii Ipo Street (Total Length = 213'). |
|
| June 24, 2010 - Pushing new 10" PVC sewerline from Pit A3, Hekaha Street, to Pit C1 on Lokowai Street. |
|
| June 24, 2010 - A.C. pavement trench restoration at Lii Ipo Street, Sta. 8+01+ to Sta. 8+91+. |
|
| June 25, 2010 - Removing pipe jack rig at Pit A3 after completing installation of new 10" PVC sewerline to Pit C1 at Lokowai Street. |
|
| June 25, 2010 - Pit A3 to Pit C1 "full moon" photo of newly installed 10" PVC sewerline. |
|
| June 25, 2010 - Removal fo pipe laeral, bury and head for Fire Hydrant L-534, Lokowai Street. |
|
| June 21, 2010 - Setting up GBM equipment at Pit A8, Hekaha Street. |
|
| June 21, 2010 - Extending new 16" PVC sewerline to SMH A2, Hekaha Street. |
|
| June 22, 2010 - Auger bit wit casing penetrating Pit K1 on Pahemo Street from Pit A8, Hekaha Street. |
|
| June 22, 2010 - Waterline "D" connection at Sta. 0+00+, Pahemo Street. |
|
| June 23, 2010 - Pushing Permalok steel casings from Pit A8, Hekaha Street, to Pit Ki, Pahemo Street. |
|
| June 23, 2010 - View of Permalok steel casings from Pit A8, Hekaha Street, towards Pit K1, Pahemo Street. |
|
| June 28, 2010 - A.C. pavement reconstruction for Sewerline "A", Hekaha Street, Sta 1+00+ to Sta. 1+41+. |
|
| June 29, 2010 - A.C. pavement reconstruction for Sewerline "A", Hekaha Street, Sta 0+58+ to Sta. 1+00+. |
|
| June 30, 2010 - A.C. pavement reconstruction for Sewerline "A", Hekaha Street, Sta. 0+23+ to Sta. 0+58+. |
|
| June 28, 2010 - Installing shoring box at Pit F4, Olepe Street and Pahemo Street intersection. |
|
| June 28, 2010 - Lightweight concrete backfill and Omni balls for Waterline "D", Pahemo Street. |
|
| June 29, 2010 - Cut and plug two fire hydrants at Lii Ipo Street, Sta. 5+55+. |
|
| June 30, 2010 - Cut and plug fire hydrant at Lokowai Street, Sta. 2+35+. |
|
| June 30, 2010 - Constructio of Pit C2 on Lokowai Street in progress. |
|